Client: Private Developer
Location: Bulphan Upminster
Project Value: £1.2million
Duration: 38 weeks
Phase 1: Clear site of existing rubble, all bushes, trees, hard standing’s and three barns / outbuildings
Phase 2: Reduce level, piling matt and ground beams for 6 no. plots. Building brickwork below beam and block floor, including DPC. Full utility connections to all of the site including crossover to approved adopted manholes. New bell mouth connection to the development for access to residents.
Phase 3: Full luxury fit out and landscaping to each plot, ready for completion and sale.