Client: Private Developer
Location: Brentwood
Duration: 35 weeks
Phase 1: Demolition of existing residential property, including removal of foundations and ground clearance.
Phase 2: Reduce level, piling and ground beams, building brickwork below beam and block floor, including DPC. Full utility connections to site and basement construction including structural waterproofing and underground car park and bin store.
.