Client: Extra Space Solution
Location: Crawley
Project Value: £180k
Duration: 8 weeks
The project included the removal of notifiable and non-notifiable asbestos within a previous school building. Excel carried out the complete strip out and removal of steel frame building, with breaking out and removal of slabs and foundation within the 6 weeks half term, careful planning in the program of the works was needed for this time sensitive project.