Call Us : 01277 355708

Client: Mizen

Location: Bulphan Upminster

Project Value: £2.8million

Duration: 72 weeks

 

A development of 19no. large luxury houses carried out over 3 phases.

Phase 1: Clear site of existing rubble, all bushes, trees and hard standing’s

Phase 2: Reduce level, piling and ground beams for 6 no. plots. Building brickwork below beam and block floor, including DPC. Full utility connections to all of the site including crossover to approved adopted manholes. New bell mouth connection to the development for access to residents.

The groundworks included deep off site drainage up to 5m, a large cut and fill exercise of 5000m3, along with all the usual groundworks of reduce levels, contamination, drainage, attenuations and head walls.

Phase 3: Construction of properties carried out by other contractors.